Stage 4: Construction of the first floor
Work starts on the first floor. Columns are erected throughout the ground floor to support the reinforced concrete slab. Brickwork and additional formwork, to house the lift, start to rise at the first-floor level. Meanwhile, protection is being installed over the waterproofing on the basement level and the interior layout begins to take shape.